ISyE 4105 Senior Design Schedule
Spring 2001
Date |
Day |
Activity |
Class |
Oral |
Written |
5-Jan |
Fri. |
Work schedule |
Yes |
|
R1 |
1/8-1/12/01 |
Mon-Fri |
Develop Alternatives |
|
|
|
1/15-1/19/01 |
Mon-Fri |
Develop Alternatives |
|
|
|
1/22-1/26/01 |
Mon-Fri |
Develop Alternatives |
|
|
|
1/29-2/2/01 |
Mon-Fri |
Evaluate Alternatives |
|
|
|
2/5-2/9/01 |
Mon-Fri |
Evaluate Alternatives |
|
|
|
2/12-2/16/01 |
Mon-Fri |
Evaluate Alternatives |
|
|
|
19-Feb |
Mon |
Practice … |
Yes |
Class |
R2 |
21-Feb |
Wed |
Tentative … |
Yes |
Class |
R2 |
23-Feb |
Fri |
Alternatives and Results |
Yes |
Class |
R2 |
26-Feb |
Mon |
Review and … |
|
|
|
28-Feb |
Wed |
Revise … |
|
|
|
2-Mar |
Fri |
Report |
|
|
|
3/5-3/9/01 |
Mon-Fri |
Spring Break |
|
|
|
12-Mar |
Mon |
Review and … |
|
|
|
14-Mar |
Wed |
Revise … |
|
|
|
16-Mar |
Fri |
Report |
|
|
|
19-Mar |
Mon |
Present … |
|
Client |
R2 |
21-Mar |
Wed |
Tentative … |
|
Client |
R2 |
23-Mar |
Fri |
Alternatives and Results |
|
Client |
R2 |
3/26-3/30/01 |
Mon-Fri |
Select Alternatives |
|
|
R3 |
2-Apr |
Mon |
Implementation Plans |
|
|
|
4-Apr |
Wed |
Implementation Plans |
|
|
|
6-Apr |
Fri |
Implementation Plans |
|
|
R3 Revised |
4/9-4/13/01 |
Mon - Fri |
Prepare Final Report |
|
|
|
16-Apr |
Mon |
Practice Final Report |
Yes |
Class |
R4 |
18-Apr |
Wed |
Practice Final Report |
Yes |
Class |
R4 |
20-Apr |
Fri |
Practice Final Report |
Yes |
Class |
R4 |
23-Apr |
Mon |
Present Final Report |
|
Client |
R4 |
25-Apr |
Wed |
Present Final Report |
|
Client |
R4 |
27-Apr |
Fri |
Present Final Report |
|
Client |
R4 |
4/30 - 5/4 |
Mon - Fri |
Complete all course requirements |
|
|
|